The short answer: 30 days
Challenges under the Procurement Act 2023 are claims in court for breach of statutory duty, set out in Part 9 of the Act. Section 106 sets the time limits:
- The general rule. You must start proceedings before the end of the period of 30 days beginning with the day you first knew, or ought to have known, about the circumstances giving rise to the claim.
- Extensions are limited. The court can extend the 30 days if it considers there is a good reason, but not beyond three months from the day you first knew or ought to have known.
- Starting means issuing a claim. The Cabinet Office's remedies guidance explains that proceedings are commenced when the court issues a claim form at the supplier's request. A letter of complaint to the buyer does not stop the clock.
When the 30 days start
The clock runs from when you knew, or ought to have known, about the problem, not from when you actually noticed it. The remedies guidance gives an example: if you think a procurement's award criteria breach the Act, you must issue your claim within 30 days of the award criteria being made available to you. Where a notice identifies a breach, the 30 days run from publication of that notice, and the guidance says the onus is on suppliers to review information in a timely manner.
That means the trigger depends on what you are challenging:
| What you want to challenge | When the clock is likely to start |
|---|---|
| A condition of participation, such as a minimum turnover or accreditation | When the tender notice or documents setting it out are published |
| The award criteria or evaluation method | When the award criteria are made available to you |
| The award decision or how your bid was scored | When you have the information that reveals the problem, typically your assessment summary or the contract award notice |
| A contract modification | When the information revealing the change is published or otherwise available |
These are general pointers. When the clock started in a real case depends on the facts, so take legal advice as soon as you suspect a problem.
The standstill period and automatic suspension
The 30-day limit is not the only deadline that matters. If you want to stop the contract being signed while your claim is decided, the standstill period is critical:
- Eight working days. The mandatory standstill period is at least eight working days, beginning with the day the contract award notice is published (Guidance: Contract Award Notices and Standstill, GOV.UK). The last day must be stated in the notice. Some contracts are exempt, although buyers can choose to apply a voluntary standstill.
- Automatic suspension. Under section 101, if you start proceedings and notify the buyer during the standstill period, the buyer cannot enter into the contract until the claim is resolved or the court lifts the suspension.
- After standstill, no automatic suspension. A claim issued or notified after the standstill period ends does not trigger the automatic suspension, even if the contract has not yet been signed. You would have to ask the court for an injunction instead.
So for an award decision, you may have 30 days to bring a claim, but only around eight working days to keep the contract from being signed automatically. Read your assessment summary the day it arrives.
What a court can order
Under the Act, the remedies depend on whether the contract has already been entered into:
- Before the contract is signed (s.103): the court can set aside a decision, such as the award decision, order the buyer to take action, such as re-assessing tenders, award damages, or make any other order it considers appropriate.
- After the contract is signed (s.104): the court can award damages, and must set the contract aside where one of the set-aside conditions in section 105 applies (subject to a public interest test), for example where the contract was signed before the end of the standstill period or during an automatic suspension.
For set-aside claims where no contract details notice was published, or that challenge a contract modification, there is also an outer limit: proceedings must start within six months of the contract being entered into or modified, even if that leaves you less than 30 days (s.106(1)).
A November 2026 ruling: Verity Healthcare v Cambridgeshire County Council
In Verity Healthcare Ltd v Cambridgeshire County Council [2026] EWHC 2830 (TCC), the High Court considered for the first time when the 30-day limit under section 106(2) starts to run. As reported by Gowling WLG:
- The challenge. The council's homecare framework required bidders to hold a CQC rating of Good or above. Verity, which did not hold that rating, argued the condition was disproportionate under section 22 of the Act.
- The timeline. The tender notice was published on Find a Tender on 15 July 2026. Verity accessed the tender portal on 18 July, wrote to the council on 21 July, received a rejection on 11 August and issued its claim on 17 August.
- The ruling. The court held that Verity ought to have known of the procurement and the condition on the day the tender notice was published, so the claim was out of time.
- Alerts and delays. A supplier relying on a third-party weekly alerts service knows it may hear of a notice days later, and that delay counts towards the 30 days. Where a requirement had been trailed during market engagement, suppliers should look out for it.
- No extension. The court said it would have refused an extension anyway: waiting for the buyer to reply to a pre-action letter was not a good reason.
Other ways to raise a concern
Court proceedings are not the only route. The Cabinet Office's Public Procurement Review Service (PPRS) investigates supplier concerns about a specific procurement, contract management or late payment. The issue must have taken place within the last two years, and its recommendations to buyers are non-binding. Raising a concern with the PPRS, or with the buyer directly, is not a court claim, so it does not stop the section 106 clock.
How to protect your position
- See notices on the day they are published. Set up daily tender alerts, or use our tender search and alert service, so you are not relying on a weekly digest.
- Read the documents straight away. Check conditions of participation and award criteria as soon as the tender notice is out, especially anything trailed during market engagement.
- Use the clarification period. If a condition looks disproportionate, ask the buyer early. It can often be resolved without a dispute.
- Diary the dates. Note the publication date of each notice, the 30-day date and the last day of standstill in the contract award notice.
- Take legal advice quickly. Do not wait for the buyer to answer a complaint before speaking to a procurement solicitor. In Verity, waiting for a pre-action letter response cost the supplier its claim.
For the wider changes the Act made to procurement, read our main guide: Procurement Act 2023: what suppliers and SMEs need to know.
How West Gate can help
- Find the work on day one: search open UK contracts free with our tender search, or set up free tender alerts for your sectors and regions.
- Outsource your bids: our bid writers handle research, compliance, writing and deadlines, and our bid management service keeps clarifications, assessment summaries and standstill dates on track. West Gate has a 90%+ win rate† and does not support competing bidders on the same opportunity. We do not give legal advice: for a challenge, use a qualified procurement solicitor.
- Talk it through: book a free 30-minute call to plan your next bid.
† Figures based on bids West Gate submitted and contracts awarded in 2025.
Frequently asked questions
How long do I have to challenge a procurement decision?
Under section 106 of the Procurement Act 2023, generally 30 days beginning with the day you first knew, or ought to have known, about the circumstances giving rise to the claim. The court can extend this for good reason, but not beyond three months.
Does the 30-day limit start when I read the tender notice?
Not necessarily. It runs from when you knew or ought to have known. In Verity Healthcare v Cambridgeshire County Council (2026), the High Court held the supplier ought to have known on the day the tender notice was published.
Can I stop the contract being signed while I challenge?
Yes, if you start proceedings and notify the buyer during the standstill period, which is at least eight working days from the contract award notice. The buyer then cannot enter into the contract unless the court lifts the suspension.
Does writing to the buyer stop the clock?
No. Proceedings start when the court issues a claim form. In Verity, waiting for the buyer to respond to a pre-action letter was not a good reason to extend the time limit.
Want us to handle this for a live bid? See our bid management and standstill support, or our full range of bid writing services.
Sources
- Procurement Act 2023, section 106: time limits on claims
- Procurement Act 2023, section 101: automatic suspension
- Guidance: Remedies (GOV.UK, updated 17 August 2026)
- Guidance: Contract Award Notices and Standstill (GOV.UK, updated 17 August 2026)
- Procurement Compliance and Oversight: Public Procurement Review Service (GOV.UK)
- Procurement Act 2023 limitation: High Court applies strict 30-day time limit (Gowling WLG, 13 November 2026)
General information, not legal advice. Always follow the tender documents and take legal advice where needed.